1.141-7T (b) Definitions.

For purposes of this section and section 1.141- 8T, the following definitions and rules apply:

(1) Available output.

The available output of a facility financed by an issue is determined by multiplying the number of units produced or to be produced by the facility in one year by the number of years in the measurement period of that facility for that issue.

(i) Generating facilities.

The number of units produced or to be produced by a generating facility in one year is determined by reference to its nameplate capacity or the equivalent (or where there is no nameplate capacity or the equivalent, its maximum capacity), which is not reduced for reserves or other unutilized capacity.

(ii) Transmission and other output facilities.

(A) In general.

For transmission, cogeneration, and other output facilities, available output must be measured in a reasonable manner to reflect capacity.

(B) Electric transmission facilities.

Measurement of the available output of all or a portion of electric transmission facilities may be determined in a manner consistent with the reporting rules and requirements for transmission networks promulgated by the Federal Energy Regulatory Commission (FERC). For example, for a transmission network, the use of aggregate load and load share ratios in a manner consistent with the requirements of the FERC may be reasonable. In addition, depending on the facts and circumstances, measurement of the available output of transmission facilities using thermal capacity or transfer capacity may be reasonable.

(iii) Special rule for facilities acquired or constructed primarily for use by private business users.

If an issuer reasonably expects on the issue date that persons that are treated as private business users will purchase more than 30 percent of the actual output of the facility financed with the issue, the Commissioner may determine the number of units produced or to be produced by the facility in one year on a reasonable basis other than by reference to nameplate capacity, such as the average expected annual output of the facility. For example, the Commissioner may treat the reasonably expected annual output of a financed peaking electric generating unit as the available output of that unit if the issuer reasonably expects, on the issue date of bonds that finance the unit, that an investor-owned utility will purchase 30 percent of the actual output of the facility under a take or pay contract, even if the amount of output purchased is less than 10 percent of the available output determined by reference to nameplate capacity. The reasonably expected annual output of the generating facility must be consistent with the capacity reported for prudent reliability purposes.

(iv) Special rule for facilities with a limited source of supply.

If a limited source of supply constrains the output of an output facility, the number of units produced or to be produced by the facility must be determined by reasonably taking into account those constraints. For example, the available output of a hydroelectric unit must be determined by reference to the reasonably expected annual flow of water through the unit.

(2) Measurement period.

The measurement period of an output facility financed by an issue is determined under section 1.141-3(g).

(3) Sale at wholesale.

For purposes of this section, a sale at wholesale means a sale of output to any person for resale.

(4) Stranded costs.

For purposes of this section, stranded costs means stranded costs as defined in 18 CFR 35.26 and costs that an issuer incurred to provide service to a wholesale or retail customer that subsequently becomes, in whole or in part, an unbundled transmission customer and that an issuer is authorized to recover by the FERC or a state regulatory authority.

(5) Take contract and take or pay contract.

A take contract is an output contract under which a purchaser agrees to pay for the output under the contract if the output facility is capable of providing the output. A take or pay contract is an output contract under which a purchaser agrees to pay for the output under the contract, whether or not the output facility is capable of providing the output.

(6) Transmission facilities.

Transmission facilities are facilities for the transmission or distribution of output. Transmission facilities include facilities necessary to provide ancillary services required to be offered as part of open access transmission tariffs under rules promulgated by the FERC under sections 205 and 206 of the Federal Power Act (16 U.S.C. 824d and 824e). Thus, if a facility also serves another function (for example, a facility that provides for operating reserves for transmission and also provides generation) an allocable portion of the facility is treated as a transmission facility.

(7) Nonqualified amount.

The nonqualified amount with respect to an issue is determined under section 141(b)(8).